Disaster Recovery
On 18 JUL 2018 a chemical plant experienced an unplanned and catastrophic release of thermal energy and flammable materials within their facility leading to extensive damage of their building and process systems. The Prime Contractor was hired to manage the entire rebuilding effort, perform building and envelope reconstruction, and assume full responsibility for return to operations. ESCO personnel were engaged as the EPC firm to rebuild the processing facility, which involved engineering and constructing all plant process-related systems including mechanical process piping, mechanical HVAC, electrical power, controls, instrumentation, and the plant DCS control system.
The plant produced its first successful batch 105 days after the catastrophe, on 03 DEC 2018.